Product Detail :
|
SCR Construction Organisation- Proposed construction of bye-pass line between MBD & RYP stations
(bye-passing Vijayawada Junction) connecting BZA-VSKP Line & BZA-KZJ line- Left Over Balance
Works & Miscellaneous works added due to extension of line to RYP yard. Works include Formation
Works (Except the location between Ch1300.0m to Ch 4550.00m, Ch 4550m to Ch 5500m,
Ch17500m to Ch19500m), Construction of LC Gate Lodge and S&T Arrangement , Compound wall,
Approach roads, Construction of drain in Rayanapadu Yard, Toe wall from Ch 4375m to Ch 4625m,
Protective works of Bridges & Miscellaneous Track Works including Supply of Ballast (Ch0m to
Ch3000m) between Mustabada and Rayanapadu Station.
|
Tender Detail : |
SCR Construction Organisation- Proposed construction of bye-pass line between MBD & RYP stations
(bye-passing Vijayawada Junction) connecting BZA-VSKP Line & BZA-KZJ line- Left Over Balance
Works & Miscellaneous works added due to extension of line to RYP yard. Works include Formation
Works (Except the location between Ch:1300.0m to Ch: 4550.00m, Ch: 4550m to Ch: 5500m,
Ch:17500m to Ch:19500m), Construction of LC Gate Lodge and S&T Arrangement , Compound wall,
Approach roads, Construction of drain in Rayanapadu Yard, Toe wall from Ch: 4375m to Ch: 4625m,
Protective works of Bridges & Miscellaneous Track Works including Supply of Ballast (Ch:0m to
Ch:3000m) between Mustabada and Rayanapadu Station. |