Product Detail :
|
The project involves the supply, installation, testing, and commissioning of a 220/33KV substation at Talaricheruvu, aimed at integrating a 275MW Battery Energy Storage System (BESS). Additionally, it includes the construction of 220 KV double circuit LILO lines from the existing 220KV Talaricheruvu to the proposed substation, replacing the current ACSR Moose conductor with ACSS Moose conductor. 220/33KV Substation, 220 KV Double Circuit LILO Lines, ACSS Moose Conductor
|
| Tender Detail : |
The project involves the supply, installation, testing, and commissioning of a 220/33KV substation at Talaricheruvu, aimed at integrating a 275MW Battery Energy Storage System (BESS). Additionally, it includes the construction of 220 KV double circuit LILO lines from the existing 220KV Talaricheruvu to the proposed substation, replacing the current ACSR Moose conductor with ACSS Moose conductor. |